Meeting Date:
|
|
Category:
|
Capital Improvements & Development |
|
|
Type:
|
|
Subject:
|
Discussion, motion and vote on motion to approve or disapprove the decrease of $46,081.00 to the Guarantee Maximum Price (GMP) Contract for Oliver Middle School Renovation. Payment will be made from the 2015 Bond Funds. B. Tolomeo |
|
|
:
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
After going through Value Engineering on the Oliver Middle School 2015 Bond Project we saw a savings of $46,081. |
|
|
Funding:
|
Not Applicable, within GMP |
|
|
Recommendation
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Courtney Cheatwood - Admin Asst to CCI |
|
Signed By: |
|
Michelle Bergwall - Chief Capital Improvement Officer |
|
Signed By: |
|
Janet Vinson - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Jerry Denton Moved, Member John Cockrell seconded to approve the Original motion 'Approve'. Upon a Roll-Call Vote being taken, the vote was: Aye: 4 Nay: 0. | The motion Carried 4 - 0 | | | Brandy Roulet | Yes | Steve Majors | Yes | Steve Allen | Yes | Jerry Denton | Yes | |
|
|
|
|
|
|