Discussion, motion and vote on motion to approve or disapprove the bid for the Spring Creek HVAC Replacement Project to OMNI Mechanical in the amount of $74,887.00 and paid for with bond fund 32. All bidding was conducted pursuant to the Oklahoma Competitive Bidding Act. R. Shepherd
|
:
|
|
Enclosure
|
Omni Mechanical bid
|
File Attachment:
|
|
Summary:
|
Bids were received and opened at 9AM, CST, Wednesday, March 30, 2022 at the Education Service Center. After reviewing, we will be accepting the bid from OMNI Mechanical in the amount of $74,887.00.
|
Funding:
|
Bond Fund 32
|
Recommendation:
|
Approve
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Courtney Cheatwood - Admin Asst to CCI
|
|
Signed By:
|
|
Larry Shackelford - Chief Operating Officer
|
|
Signed By:
|
|
Chuck Perry - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Brandy Roulet Moved, Member John Cockrell seconded to approve the Original motion 'Approve'. Upon a Roll-Call Vote being taken, the vote was: Aye: 4 Nay: 0. | The motion Carried 4 - 0 | | | Debbie Taylor | Yes | Brandy Roulet | Yes | John Cockrell | Yes | Jerry Denton | Yes | |
|
|
|
|
|
|